Biogas Bottling Plant Consultancy

Register

krishnaenergy

Senior Member
Dear Friends,

We got many mails across the globe regarding biogas purification and compression unit. The profile of 400m3 compressed biogas plant is herewith mentioned for better understand and minimising the enquiry in this regards.

1. Cost of biogas digester, purification plant and bottling unit: Rs.80 lakhs
2. Purified gas (Methane/CNG) production per day: 170kg
3. Bio-mannure production per day: 1.5 Ton
4. CDM benefits per annum: 1200 CER
5. Annual earnings from bottled gas: Rs.18.60 lakhs
6. Annual earnings from bio-manure:Rs.16.20 lakhs
7. Annual earnings from CDM @10Euro/CER: Rs.7.20 lakhs
8. Expenditures per annum including raw materials, salary, consumables, maintainance, interest etc: Rs.20.00 lakhs
9. Subsidy from MNRE: 40% of project cost
10. Payback period: 3-4 years

We offer turnkey contract services to set up the plant and preparing Detailed Project Report (DPR) by highly qualified and experienced consultants. The data in the report are reliable and up-to-date collected from suppliers and manufacturers. As we want to promote this technology in larger scale for serving to set up the plant on turnkey basis, we are charging INR.11,030/- (USD500) including service tax @10.30% for Detailed Project Report (DPR) and Rs.2,00,000/- for process knowledge, training to your personnel and turnkey contract services. One can get a grant of INR.100,000/- from MNRE for DPR preparation.

Content of Detailed Project Report (DPR) on Biogas Purification & Bottling System

1. Project at a glance
2. Board Outline of the Project
3. Company Profile (You have to Fill up)
4. Project Background and Introduction
5. General Information
6. Brief Description of the Project (Activity & Purpose)
7. Current status of the work
8. Details of approach intended to be adopted
9. Oppertunity
10. Project’s contribution to sustainable development
11. Evaluation of environmental impacts, Effect on Biological environment, Effect on Water quality, Effect on Air quality, Effect on land environment/soil, Effect on Noise pollution, Socio-economic effect and Aesthetic environment
12. Emissions and CDM benefits
13. Project Environment Management
14. Salient features of the project, Biomass availability, Biogas export and Sale of By-products.
15. Basis and Presumptions
16. Market Demand and Marketing Aspect
17. Production Capacity & Target
18. Process Technology and Technical details
19. Product description & uses
20. Requirement of Land Area, Built up Area, Plant layout.
21. Plant Location and Infrastructures
22. Plant Facilities with specifications
23. Raw Materials, Sources and Specifications
24. Utilities and services
25. Manpower Requirement and Planning
26. Project Implementation Schedule with Bar chart
27. Operational parameters like total biogas/methane generated, power consumed by the plant auxiliaries, and efficiency of the plant activity.
28. Financial Analysis
29. Conclusion
30. Annexure: Cost of Project, Means of Finance, Subsidies, Debt Equity ratio, Assumptions and Projections, Profitability Analysis with 100% capacity utilization, Profitability Analysis with 80% capacity utilization, Profitability Projection for Ten Years, Taxation Schedule, Proforma Balance Sheet, Fund Flow Statement, Working Capital Projections, Depreciation Schedule, Break Even point, Payback Period, Interest and Repayment Schedule, Schedule of Salary and wages, Financial Ratio etc.

This can be had through your email on payment in the shape of Demand Draft in favour of “Krishna Engineers & Consultants” payable at Bhubaneswar. You can also deposit the same in our ICICI current account No: 006105002038.

We look forward an early response from your side. Please feel free to ask any question in this project.

With Regards.

Pramod Hati
Krishna Engineers & Consultants
 
Last edited by a moderator:

vishnu_nkd

New Member
biogas bottling

CDM benefits per annum: 1200 CER what it means of
and the total cost of the project you said that 80lakhs but 40% subsidy will provide through mner so is it requires only that remaining amount or with subsidy also we invest 80 lakhs
 

krishnaenergy

Senior Member
Carbon Development Mechanism (CDM) benefits can be availed in this project as this will replace fossile fuels with renewable energy. The total project cost is Rs.80 lakhs. Subsidy is maximum 40%, minimum promoters invest 20% and rest is the maximum term loan.
 

mvsvasu

New Member
information

if u can send your email id and phone no so that i can contact u.


- vasu
 
Last edited by a moderator:

phani999

New Member
biogas bottling

hi

iam phanirajdesai i want promote the biogas for commercial is it is possible

thanking you


phanirajdesai
 
Last edited by a moderator:

moukwele

New Member
Biogas Purification & Bottling System

Dear Sir,

Biogas Purification & Bottling System on turnkey basis has fully retained my attention and I'm eager to make money with your esteemed company within our country. As business engineering consultant, my job will be to push this project within our local market and to make contract for your company. It’s also important to inform you that I'm qualified for CDM projects.

Please kindly send me any document, picture or brochures of your past experience.

I'm looking forward to hearing from you.

Best regards,
 
Last edited by a moderator:

krishnaenergy

Senior Member
Dear Friends,

Now we are able to render our services for biogas purification, CO2 recovery system, Methane bottling, Pretreatment plant for maximum biogas yields and biogas from energy grass. We can also help you for energy grass plantation for your biogas project or pellet plants. You can contact us at mail id: krishnaenergy(a)gmail.com/ pramod_hati(a)krishnaenergy.com. You can call Mr. Pramod Hati over his cell phone: +91-9437256123.

Thanks and regards.
 

krishnaenergy

Senior Member
Intelligent Biogas Project

Dear Friends,

Now we are able to render our services for biogas purification, CO2 recovery system, Methane bottling, Pretreatment plant for maximum biogas yields and biogas from energy grass. We can also help you for energy grass plantation for your biogas project or pellet plants. You can contact us at mail id: krishnaenergy(a)gmail.com/ pramod_hati(a)krishnaenergy.com. You can call Mr. Pramod Hati over his cell phone: +91-9437256123.

Thanks and regards.
 

nikki25123

New Member
i want to open a new biogas botteling plant in my city can u give me detail about , through make a call

contact no. 09926831470
 

rams25289

New Member
I need a profile for 1500 m3 biogas botteling plant. already having land and cow dung available. give me the detials of the investment needed for 1500m3. for detail project report how i should send the amount and how much
 

krishnaenergy

Senior Member
Steps for Project Implemmentation

Dear Sirs,

Please find the steps followed for the implementation of the project.

1. Company registration
2. Printing of Letter Head and rubber stamps of the company
3. Survey for biomass assessment
4. Preparing Detailed Project Report
5. Registration at DIC
6. Registration of Land which will be used for the purpose
7. Developing a approved Map/ sketch of the land
8. Contact your bank for loan purpose

You will prepare the following documents for the loan purpose.
1. Your Asset and liability
2. Balance Sheet and Profit Loss Statement for last three consecutive years
3. Your Net worth at present
4. Document w.r.t. sources of promoters' contribution
5. Your Family history describing the activity of all the family member and relatives
6. Proof of Collateral security which you can place to bank

Besides this you will require the following documents/ designed papers for further proceeding and approvals / clearances from different departments. We can render our services for developing the required documents.

1. Preparing and approval of Civil Drawing and Estimation
2. Preparing Plant Layout
3. Preparing and approval of Electrical Layout and Estimation
4. Preparing Process Layout
5. Application to State Electricity department along with drawing and estimation
6. Clearance from State Pollution Control board along with all designed documents
7. Consent letter from Government to set up an industrial unit along with all designed documents
8. Approval of constructional activity and building plan from local authority
9. Clearances from Central Ground Water Board

Besides these you will also require following documents.
1. MoU with Farmers/ organisations to supply biomass
2. MoU with Industries/ Commercial consumers to purchase the Bottled biogas

Our charges for turnkey consultancy services for design, engineering, drawing, prepare all required technical documents and supporting documents, selection of technology, selection of vendors for different equipments/ machineries, supervising at manufacturer’s site, supervising and coordinating during erection and commissioning, preparing O&M manual etc. will be Rs.500,000/- plus service tax @12.36%.

For DPR the charges will be Rs.28090/- including service tax. To place the order for DPR, you have to transfer/ deposit the funds in our current account and can had the soft copy of your DPR within 7-10 days.

Thanks and regards.
Pramod Hati
 

vikram_dahiya

New Member
Dear Friends,

We got many mails across the globe regarding biogas purification and compression unit. The profile of 400m3 compressed biogas plant is herewith mentioned for better understand and minimising the enquiry in this regards.

1. Cost of biogas digester, purification plant and bottling unit: Rs.80 lakhs
2. Purified gas (Methane/CNG) production per day: 170kg
3. Bio-mannure production per day: 1.5 Ton
4. CDM benefits per annum: 1200 CER
5. Annual earnings from bottled gas: Rs.18.60 lakhs
6. Annual earnings from bio-manure:Rs.16.20 lakhs
7. Annual earnings from CDM @10Euro/CER: Rs.7.20 lakhs
8. Expenditures per annum including raw materials, salary, consumables, maintainance, interest etc: Rs.20.00 lakhs
9. Subsidy from MNRE: 40% of project cost
10. Payback period: 3-4 years

We offer turnkey contract services to set up the plant and preparing Detailed Project Report (DPR) by highly qualified and experienced consultants. The data in the report are reliable and up-to-date collected from suppliers and manufacturers. As we want to promote this technology in larger scale for serving to set up the plant on turnkey basis, we are charging INR.11,030/- (USD500) including service tax @10.30% for Detailed Project Report (DPR) and Rs.2,00,000/- for process knowledge, training to your personnel and turnkey contract services. One can get a grant of INR.100,000/- from MNRE for DPR preparation.

Content of Detailed Project Report (DPR) on Biogas Purification & Bottling System

1. Project at a glance
2. Board Outline of the Project
3. Company Profile (You have to Fill up)
4. Project Background and Introduction
5. General Information
6. Brief Description of the Project (Activity & Purpose)
7. Current status of the work
8. Details of approach intended to be adopted
9. Oppertunity
10. Project’s contribution to sustainable development
11. Evaluation of environmental impacts, Effect on Biological environment, Effect on Water quality, Effect on Air quality, Effect on land environment/soil, Effect on Noise pollution, Socio-economic effect and Aesthetic environment
12. Emissions and CDM benefits
13. Project Environment Management
14. Salient features of the project, Biomass availability, Biogas export and Sale of By-products.
15. Basis and Presumptions
16. Market Demand and Marketing Aspect
17. Production Capacity & Target
18. Process Technology and Technical details
19. Product description & uses
20. Requirement of Land Area, Built up Area, Plant layout.
21. Plant Location and Infrastructures
22. Plant Facilities with specifications
23. Raw Materials, Sources and Specifications
24. Utilities and services
25. Manpower Requirement and Planning
26. Project Implementation Schedule with Bar chart
27. Operational parameters like total biogas/methane generated, power consumed by the plant auxiliaries, and efficiency of the plant activity.
28. Financial Analysis
29. Conclusion
30. Annexure: Cost of Project, Means of Finance, Subsidies, Debt Equity ratio, Assumptions and Projections, Profitability Analysis with 100% capacity utilization, Profitability Analysis with 80% capacity utilization, Profitability Projection for Ten Years, Taxation Schedule, Proforma Balance Sheet, Fund Flow Statement, Working Capital Projections, Depreciation Schedule, Break Even point, Payback Period, Interest and Repayment Schedule, Schedule of Salary and wages, Financial Ratio etc.

This can be had through your email on payment in the shape of Demand Draft in favour of “Krishna Engineers & Consultants” payable at Bhubaneswar. You can also deposit the same in our ICICI current account No: 006105002038.

We look forward an early response from your side. Please feel free to ask any question in this project.

With Regards.

Pramod Hati
Krishna Engineers & Consultants
Dear Sir

What is the Cost of 3000 M3 biogas digester, purification plant and bottling unit.
thanks and regards
vikram dahiya
 